Gilmerton New Church 

 


welcome
more about us
info for parents

the hub

schools activities
create arts activities
cross sports

CSCA 08

mad weekends
sports camps

message board
prayer requests

reef group

related links & sites
how to contact us



Click on any of the thumbnails to view bigger photos!


February 4th 2008 - The Hub

Here are some photos of the finished project!




















































































































Return to top



December 12th

Heating is all on, floor coverings are fitted everywhere except stairs and mezzanine - these areas will be done over the next week. Decorating and external works are progressing well. White goods have arrived and are in the kitchen. Plumbing & electrical work is continuing. Furniture has been ordered and will arrive mid-January. Audio visual works will be completed in the New Year.







































































Return to top


November 28th

Decorating is progressing well, heating is partially on and cleaning of the stained glass is in progress. Flooring in the kitchen, corridor and toilets will go down next week with carpeting going down once the decorating is complete. Audio visual connections are being made with the final installation taking place in January.




































































Return to top

 

November 14th

Decorating has started, the light fittings are almost in place, folding screen doors are being fitted and the heating should go on next week. Furniture and floor coverings have been ordered. External works to the grounds will be commencing shortly.

























































Return to top

October 31st 2007

Low surface temperature radiators are almost all fitted. Sanitary ware and toilet cubicles are currently being installed. The kitchen installation is progressing and the café counter is being built. Decorating will be commencing towards the middle of November.







































Return to top

October 24th 2007

We now have lighting in the building which makes a huge difference. The kitchen is partly installed, the entire floor has been sheeted, all other works are continuing satisfactorily.

















































Return to top

October 3rd 2007

Here are the photos from the latest site meeting. The walls are being sheeted, sanitary ware has arrived, electrical sockets/switches etc are being fitted and all the light fittings are now on site (as you can see from the architect holding one up to show us what it looks like above the mezzanine!)


































Return to top
 

September 19th 2007


















































































Return to top


September 5th 2007

Here are the photos from the latest site meeting!


























































Return to top

 

August 23rd 2007

Here are the latest photo's taken at yesterdays site meeting! The wiring and plumbing works are well under way. The mezzanine floor is taking shape.....although still accessed by a ladder! Roofing works are in progress and the joiners will soon be starting to sheet out the walls.
























































Return to top


August 13th 2007

The steelwork for the mezzanine level is now in place. Plumbing, electrical and roofing work are all taking place at the moment and the next phase of joinery work should begin soon.






July 11th 2007

The base for the stage is now in place and the framing is almost complete between the main hall and the side areas. Rot treatment works are in progress (as you can see by the removal of the ceilings and paneling round the walls), electrical installation starts next week and the steelwork for the mezzanine level is also due to arrive soon.


Return to top


26th June 2007

Work is progressing well. The roof is now on the rear area, framing is in place for the toilets and they are working on the framing for the side partitions in the sanctuary. Heating pipes are being laid and concrete being poured for the steels for the mezzanine floor! It's a definite hive of activity!!


June 13th 2007




 

Before work began




Return to top









Thank you for visiting our website. If you have any suggestions about this website or experience any problems viewing it please email